This timeline represents our best estimate of how the project will move forward, subject to receiving the appropriate leases and permits from the relevant authorities.

2021

  • Project scoping and feasibility studies
  • Early consultation with regulators, communities and other stakeholders
  • Crown Estate announces attention to grant lease subject to HRA
  • Onshore and offshore surveys

2022

  • Environmental Impact Assessment Scoping Report submitted to Natural Resources Wales
  • Environmental Impact Scoping Opinion received from Natural Resources Wales
  • Onshore and offshore surveys
  • Technology selection process

2023

  • Technology selection process
  • Design optimisation and procurement
  • Opening of Pembroke Dock office

2024

  • Public consultation
  • Preparation of planning and environmental information and reports

2025

  • Ongoing design and procurement
  • Fabrication

2026

  • Fabrication

2027

  • Installation